(11-17-26) After months of public silence, Celina’s new firehouse is moving again. City officials have selected the team of Garmann Miller of Minster and Mull & Weithman Architects Inc. of Columbus to design the new 22,000-square-foot firehouse on a 1.8-acre vacant lot at 301 Grand Lake Road.

The total project cost could run anywhere from $12.5 million to $14.5 million, Mayor Jeff Hazel told The Daily Standard on Monday afternoon. The architectural firms will likely earn 7 percent of the total project cost.

No contract has been signed yet.

Hazel told the Standard…

“They came as a team, so that’s who ultimately was selected. We’re working on … getting a contract, but we haven’t signed the contract yet,” Hazel said.

How the pick was made

Eleven firms submitted proposals. The selection panel narrowed the field to four, then settled unanimously on Garmann Miller.

Hazel told them Standard-

“We had some really great firms. Any one of the 11 firms that submitted could have done that. We got down to four. Any one of the four could do that, but we all feel confident because of the closeness and proximity of Garmann Miller. We believe that they would be closer to be on site to deal with any designs, any questions. We just believe that they’re the best fit for our community and the fire department.”

The panel that reviewed the firms was Hazel, Fire Chief Brian Davis and three city councilors — personnel and finance chairperson Eric Clausen, safety services chairperson Matt Gray and buildings and grounds committee chairperson Chris Doseck.

Hazel said the team brings the expertise of both companies. Mull & Weithman, which specializes in public safety design, is the firm that completed the feasibility study of the City Hall and fire department — a study the city council authorized in May 2024.

The site

The firehouse will built on the former Orchard Tree property on Grand Lake Road, land the city bought earlier this year. The site was formerly owned by Mercer Health, and the purchase was facilitated by public grants, according to city council minutes from March, when Mayor Hazel reported the purchase was being finalized.

The city spent months searching for the right location. The key requirement: a spot that puts firefighters within a four-minute response time for the majority of calls. When the purchase was announced in March, the new station was projected at 21,000 square feet; the plan now stands at 22,000.

The backstory

The announcement is the first public movement on the project since the land purchase — and it comes after months of pressure for answers. The Mercer County Outlook has been pressing city officials for updates on the firehouse since the spring, including an open letter to city officials, and renewed the request in August after more than five months without a public update.

Sources: The Daily Standard, Tuesday, Nov. 17, 2026 (front page; article continues on page 2A); Celina City Council minutes, March 9, 2026 (site purchase) and May 13, 2024 (feasibility study authorization); City of Celina (Fire Chief Brian Davis appointment, July 2025).

Key Project Details

  • Facility Size. The new multimillion-dollar firehouse will span approximately 22,000 square feet.
  • Location. It will be constructed on a 1.8-acre vacant lot on Grand Lake Road, the former site of the Orchard Tree restaurant.
  • Site Acquisition. In February 2026, Celina City Council approved purchasing the 501 Grand Lake Road property from Mercer Health for $470,247.50, along with adjoining parcels, after determining the location met the department’s 4-minute response time standard.
  • Background. Mull & Weithman Architects previously conducted a feasibility study for the city in late 2025 evaluating whether to renovate the existing downtown fire station at City Hall or relocate to a new site